| Power Industry |
|
|
|
|
Bangladesh is progressing through a phase of development where automation is the key to its economy and business. As the country continues to industrialise the importance of power generation and electricity supply becomes a key government priority. Power Industry in recent timesAt present, 48.5% of the total population of Bangladesh is enjoying the electric facilities. As of April 2010, the total numbers of transmission and distribution lines are recorded to 8,359 km and 266,460 km respectively. However, 53,281 villages have been electrified so far. In Bangladesh per capita generation is 220 KW hr which is comparatively lower than other developed countries in the world. Recent Status:
Figures other than Installed Capacity and Maximum Generation are of June 2010.Source: Bangladesh Economic Review 2011(Bangla version), www.mof.gov.bd
Public and private sector produces 63% and 37% of electricity respectively. Public sector produces electricity through Bangladesh Power Development Board (BPDB), Ashuganj Power Station Company LTD (APSCL) and Electricity Generation Company of Bangladesh (EGCB). On the other hand, private sector produces power through small independent power producers and rental that government buys at a constant price. BPDB individually produces 46% of the total production. Electricity Production, 2010, by Sector
1Bangladesh Power Development Board2Ashuganj Power Station Company Limited3Electricity Generation Company of Bangladesh4Smal Independent Power Producer5Rural Electrification BoardSource: Power and Energy Sector Development Roadmap (June 2010), Ministry of FinanceElectricity Production (Public), 2010, by % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Sl. no. | Name of power plant | Fuel type | Installed capacity (MW) | Generation capacity (MW) | Established | Contracted levelized tariff (US cents/kWh) |
|
1
|
Khulna Power Company Ltd. (KPCL), Engine Generator |
F.Oil
|
110
|
110
|
1998
|
5.83 (For liquid fuel) 4.40 (For gas)
|
|
2
|
Baghabari, WESTMONT, GT |
Gas
|
90
|
90
|
1999
|
4.31
|
|
3
|
NEPC Consortium, Gas Generator |
Gas
|
110
|
110
|
1999
|
4.41
|
|
4
|
Rural Power Co. Ltd. (RPCL), GT |
Gas
|
140
|
140
|
2001
|
4.30
|
|
5
|
AES, Haripur CC |
Gas
|
360
|
360
|
2001 (SC) 2001 (CC)
|
2.73*
|
|
6
|
AES, Meghnaghat CC |
Gas
|
450
|
450
|
2002
|
2.79*
|
|
7
|
Summit Power Co. Ltd. |
Gas
|
30
|
30
|
2003
|
|
|
|
Total |
|
1,290
|
1,290
|
|
|
* Based on indicative Gas price: 2.40 US$/GJ.
Source: Ministry of Power, Energy and Mineral Resources
Power Industry Development Plan
In order to realize the government’s vision to provide electricity to most of the population at a reasonable price and to achieve overall socio-economic development of the country, the government of Bangladesh has initiated a Power and Energy Sector Development Roadmap (2010-2021) which targeted to produce 8,500 MW by 2013, 11,500 MW by 2015 and 20,000 MW by 2021. However, to ensure overall and balanced development of this sector government has taken various plans in terms of duration. The plans have been developed based on a techno-economic analysis and a least-cost option. These plans include balanced development in generation, transmission and the distribution system to achieve a desired level of reliability of supply. A summary of the development plan is given as follows:
Short Term Plan (2011)
According to the short-term plan, liquid fuel based 12-24 months of implementable power stations will be established. However, government has initiated to implement a power station with a capacity of 920 MW.
Mid Term Plan (2012-2015)
Under this plan, government has taken into account to establish 3 to 5 years of implementable coil based power stations with a capacity of 2,600 MW to the total capacity of 7,714 MW.
Long Term Plan
As of the Power and Energy Development Roadmap (2010-2021), government expects to meet the desire destination (20,000 MW by the year 2021) through the increment of 10% production per year towards reaching the per capita consumption to 600 Kw.
Projected Surplus Electricity Production (Yearwise)
|
Year
|
Public sector
|
public sector
|
Total (MW)
|
|
2011
|
920
|
-
|
920
|
|
2012
|
505
|
1,764
|
2,269
|
|
2013
|
725
|
950
|
1,675
|
|
2014
|
1,170
|
-
|
1,170
|
|
2015
|
-
|
2,600
|
2,600
|
|
Total surplus
|
9,426
|
||
Source: Power and Energy Sector Development Roadmap (June 2010), Ministry of Finance
Projected Electricity Demand and Supply (Yearwise)
|
Projected data
|
2011
|
2012
|
2013
|
2014
|
2015
|
|
Projected demand (MW)
|
6,298
|
6,832
|
7,709
|
8,699
|
9,812
|
|
Capacity retired (MW)
|
-
|
-
|
448
|
378
|
-
|
|
Projected supply (MW)
(excluding quick rental)
|
5,177
|
7,029
|
8,326
|
9,545
|
11,625
|
|
Projected supply (MW)
(including quick rental)
|
6,363
|
8,683
|
9,764
|
10,527
|
12,601
|
|
Shortage/surplus (MW)
(exlcuding quick rental)
|
-1,121
|
197
|
617
|
846
|
1,813
|
|
Shortage/surplus (MW)
(including quick rental)
|
65
|
1,851
|
2,055
|
1,822
|
2,789
|
Source: Power and Energy Sector Development Roadmap (June 2010), Ministry of Finance
Bangladesh is steadily climbing up the development ladder. Energy and power needs to act as a key catalyst in helping Bangladesh in this endeavour. Industries are being automated and the country is gradually moving from a labor-intensive economy to a capital intensive one. Electricity and power are vital to the nation at such a stage. Bangladesh has a vast market as far as power and electricity is concerned and good prospects for constructing power generation plants exist in the country in terms of resources available and government policies.